NEW QUESTION # 44
In project management, what data can be copied from a project template during creation of a new project?
NOTE: There are 3 correct answers to this question.
- A. Checklist
- B. Dates
- C. Project structure
- D. Authorizations
- E. Responsible organizational unit
Answer: C,D,E
NEW QUESTION # 45
Which method can you use to update multiple values simultaneously in capacity planning for portfolio management?
- A. Distribution function
- B. XML upload
- C. Drag and drop
- D. Mass update
Answer: A
NEW QUESTION # 46
What data influence the bottom-up scheduling of a project in portfolio management?
NOTE: There are 3 correct answers to this question.
- A. Relationships between tasks
- B. Project type
- C. Relationships between phases
- D. Duration of tasks
- E. Role demands
Answer: A,C,D
NEW QUESTION # 47
How can an existing project management project be integrated with SAP controlling?
NOTE: There are 2 correct answers to this question.
- A. Assign the project roles to an existing internal order manually
- B. Assign the project definition to an existing PS project definition manually
- C. Transfer the project structure element to project system (PS)
- D. Transfer the project structure element internal orders
Answer: A,B
NEW QUESTION # 48
How are capacity planning values rolled up along the bucket hierarchy?
- A. Project values are rolled up directly to buckets
- B. Item values are rolled up to buckets via the review
- C. Item values are rolled up to buckets via the collection
- D. Item values are rolled up directly to buckets
Answer: D
NEW QUESTION # 49
Where can you use the BCV report in SAP PPM?
NOTE: There are 3 correct answers to this question.
- A. Metrics
- B. Review
- C. Scoring model
- D. Bucket
- E. Item
Answer: B,D,E
NEW QUESTION # 50
You have created a custom field and want to add this field to the item dashboard.
Where do you have to select the field to achieve this?
NOTE: There are correct answers to this question.
- A. In the item dashboard settings
- B. In customizing for item dashboard fields
- C. In the Launchpad settings for the item dashboard
- D. In the BCV settings for the item dashboard
Answer: A,B
NEW QUESTION # 51
You want to use a customer-specific status for items.
How do you configure the status in customizing?
- A. Create the status and status transition within the portfolio type
Assign the portfolio item type to the portfolio type - B. Create a business add-in (BAdi) for customer-specific status management Activate the BAdi for the portfolio item type
- C. Create the status
Assign the status to a portfolio item type
Specify the status transitions with respect the portfolio item type - D. Create a status profile for the portfolio item objet type
Create the status within the status profile
Assign the status profile to a portfolio item type
Answer: C
NEW QUESTION # 52
For which of the following object types can you define questionnaires?
NOTE: There are 2 correct answers to this question
- A. Bucket
- B. Portfolio item
- C. Project management project
- D. Initiative
Answer: B,D
NEW QUESTION # 53
What influences whether an items is displayed in a specific dashboard scope?
NOTE: There are 3 correct answers to this question
- A. Item status group
- B. Escalation flag
- C. Proposal flag
- D. Decision point status
- E. Priority
Answer: A,B,C
NEW QUESTION # 54
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?
- A. The role demand for the timeframe is too low
- B. The assigned effort for either of the resource assigned is to high
- C. The edit in parallel indicator is inactive for the role type in customizing
- D. The flexible Assignment indicator is active for the rile type in customizing
Answer: C
NEW QUESTION # 55
In project management, a WBS element for accounting integration was created automatically.
What is used to calculate the planned costs of this WBS element?
NOTE: There are 3 correct answers to this question
- A. Duration planned on project tasks
- B. Demand planned on project roles
- C. Staffing of work in the role
- D. Work planned on project task
Answer: B,D
NEW QUESTION # 56
Which of the following are search criteria In Resource Search in Project Management?
NOTE: There are 2 correct answers to this question.
- A. plants
- B. Qualifications
- C. Work centers
- D. Organizational units
Answer: B,D
NEW QUESTION # 57
What is the priority field in the project definition of a project management project used for?
- A. To support the evaluation of projects
- B. To determine the approval authorizations required
- C. To restrict the selection of project types
- D. To determine the scheduled dates for the project
Answer: A
NEW QUESTION # 58
You want to distribute capacity requirements in a project management project?
How can you distribute the values?
NOTE: There are 3 correct answers to this question
- A. Enter the vales manually
- B. Copy values from resource assignments
- C. Apply a distribution rule
- D. Use a distribution function
- E. Update the capacity requirements from the roll-up of task requirements
Answer: A,D,E
NEW QUESTION # 59
Bucket A contains items and current located in bucket P1.
How do you move bucket A including the items to bucket p2.
- A. Select bucket A from the bucket dashboard
Change the parent bucket field from P1 to P2 - B. Select bucket p2 in the move function as a target for bucket A
Execute the move function - C. Create a new bucket in bucket P2
Move all items from bucket A to the new bucket
Delete bucket A and rename the new bucket - D. Move all items from bucket A to bucket p2.
Move the empty bucket A to p2
Copy all bucket A items from bucket p2 to bucket A
Answer: C
NEW QUESTION # 60
The probability technical success filed is enabled for questionnaires. You have defined a questionnaire for portfolio items In customizing. When you want to fill out the questionnaire for the probability technical success filed an error message is displayed.
What is the reason for the error message?
- A. The field service configuration of the item is missing
- B. The master switch for the interface settings for questionnaires it turned off
- C. The field service configuration of the parent bucket of the item is missing
- D. The probability technical success field is configured as read only in the field control
Answer: C
NEW QUESTION # 61
You have defined a financial view for portfolio bucket so that financial values are rolled up.
Which of the following are possible sources for the rollup?
NOTE: There are 3 correct answers to this question
- A. Project management projects
- B. Project system project
- C. Standalone items
- D. Initiatives
Answer: C,D
NEW QUESTION # 62
How can you trigger a workflow for a portfolio item?
NOTE: There are 2 correct answers to this question.
- A. Change the item status
- B. Exceed the budget of the item
- C. Change the master data of the item
- D. Choose the start workflow button
Answer: A,C
NEW QUESTION # 63
......
SAP C-S4PPM-2021 exam is designed to test the candidate's knowledge and skills in the area of SAP S/4HANA Portfolio and Project Management. Certified Application Associate - SAP S/4HANA Portfolio and Project Management certification is ideal for professionals who want to demonstrate their expertise in implementing and managing projects using SAP S/4HANA. C_S4PPM_2021 exam covers various topics such as project planning, execution, monitoring, and controlling, as well as portfolio management, resource management, and financial management. C_S4PPM_2021 exam also tests the candidate's knowledge of SAP Activate methodology and agile project management principles.