NEW QUESTION # 38
Resources
Which of the following transactions can you use to post actual cost for external processing.
Note : there are 2 correct answer for this question.

  • A. Approval of a good receipt.
  • B. Creating a purchase order.
  • C. Creating a service entry sheet
  • D. Posting a goods receipt
  • E. Approval of a service entry sheet

Answer: D,E


NEW QUESTION # 39
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

  • A. Set up the requirement date manually as February 5.
  • B. Set up the requirement date aligned with the activity start date and an offset of 5 days
  • C. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
  • D. Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Answer: D


NEW QUESTION # 40
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

  • A. Project Builder
  • B. Easy Cost Planning
  • C. Schedule Manager
  • D. Project planning board

Answer: A,D


NEW QUESTION # 41
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.

  • A. Project-relevant purchase orders
  • B. Capacity requirements
  • C. Production orders assigned to WBS elements
  • D. Maintenance orders assigned to an activity

Answer: B,D


NEW QUESTION # 42
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?

  • A. Results analysis key
  • B. Investment profile
  • C. Settlement rule
  • D. Costing sheet

Answer: D


NEW QUESTION # 43
Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?

  • A. Use mass change within the project Builder (CJ20N).
  • B. Use mass change (CNMASS) in the project system.
  • C. Double the work of each internal activity, one after another, in the project Builder.
  • D. Double the capacity in the work center.

Answer: B


NEW QUESTION # 44
Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?

  • A. management in the project definition. Enter the budget in the master data of the top WBS element.
  • B. Activate availability control For projects in the control area. Enter the plan data for each WBS element.
  • C. Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.
  • D. Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.
  • E. Activate commitment

Answer: C


NEW QUESTION # 45
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question

  • A. Project versions are mandatory for Milestone Trend Analysis (MTA)
  • B. Manually Created project versions always require a project version profile
  • C. Project versions can be created automatically based on user status
  • D. Project versions can be changed

Answer: A,C


NEW QUESTION # 46
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

  • A. The network activity is assigned to a WBS element
  • B. The material master of the component must permit project stock management
  • C. A procurement indicator must be assigned to the activity
  • D. The network is assigned to a sales order item
  • E. The Project Stock indicator is set in the project definition (non-valuated or valuated)

Answer: A,B,E


NEW QUESTION # 47
Which objects can be used to specify settlement rules? Note: There are 2 correct Answers to this question.

  • A. Network header for activity-account-assigned networks
  • B. WBS elements
  • C. Standard WBS elements
  • D. Network activity for activity-account-assigned networks

Answer: A,B


NEW QUESTION # 48
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.

  • A. By searching for the status profile
  • B. By searching for the individual status
  • C. By searching via status combination code
  • D. By searching via status selection profile

Answer: A,B


NEW QUESTION # 49
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.

  • A. The material master of the component must permit project stock management.
  • B. A procurement indicator must be assigned to the activity.
  • C. The network is assigned to a sales order item.
  • D. The network activity is assigned to a WBS element.
  • E. The Project Stock indicator is set in the project definition (non-valuated or valuated).

Answer: A,B,E


NEW QUESTION # 50
How can you record external service activities with service master data? Note: There are 2 correct Answers to this question.

  • A. Post a goods receipt in the goods movement application (MIGO).
  • B. Create a service entry sheet.
  • C. Confirm the network activity for external services.
  • D. Confirm the activities in the Cross-Application Time Sheet (CATS).

Answer: B,D


NEW QUESTION # 51
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. Structure overview
  • B. Capacity load work center view
  • C. Extended capacity evaluation
  • D. Individual overview capacity requirements

Answer: B


NEW QUESTION # 52
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

  • A. You can always maintain the actual start and finish date of a WBS element
  • B. You can only maintain the actual start of a WBS element if the finish date is not maintained
  • C. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
  • D. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"

Answer: B,D


NEW QUESTION # 53
For which objects can billing plans be created? Note: There are 2 correct answers to this question

  • A. Sales order items
  • B. WBS elements
  • C. Project definition
  • D. Milestones

Answer: B,D


NEW QUESTION # 54
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

  • A. The network profile
  • B. The table of MRP controllers
  • C. The scheduling parameters for the network
  • D. The control key

Answer: C


NEW QUESTION # 55
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question

  • A. If the appropriate reduction type is set in the parameters for network scheduling
  • B. If the reduction strategy is set in the network header
  • C. If the maximum reduction level is less than 100
  • D. If the reduction strategy is set in each activity

Answer: A,C


NEW QUESTION # 56
The various work packages in the project are described as individual______________. Choose the correct answer.

  • A. Activities
  • B. Tasks
  • C. WBS elements
  • D. Project definitions

Answer: C


NEW QUESTION # 57
Project Structures
You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?

  • A. The tab user fields is invisible.
  • B. The field key is the default value for the WBS element and the activities too.
  • C. The field key is hard coded in the WBS element.
  • D. The field key is the default value only for the WBS element.

Answer: B


NEW QUESTION # 58
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

  • A. Control key of an activity
  • B. Capacity planner group in the network header
  • C. Scheduling and distribution key
  • D. Scheduling and capacity category

Answer: A